CHANGE ORDER
Customer
| Description | Qty | Rate | Amount |
|---|
Schedule change
0 days
Terms
Added work is billed with the next progress payment. Work in this change order starts after both sides sign.
Made with Hitch Invoice
This change order template adds and removes work and works out the new contract total and finish date for you. Both of you sign before the extra work starts. Free, no sign-up.
Your business
CHANGE ORDER
Customer
| Description | Qty | Rate | Amount |
|---|
Schedule change
0 days
Terms
Added work is billed with the next progress payment. Work in this change order starts after both sides sign.
Made with Hitch Invoice
Your color
Every style prints the same details. Your pick is saved for your next document.
Draft saved on this device.
New contract total
$0.00
Last updated: . Sources: Change order math done in your browser.
A remodeler's contract for a hall bathroom was $18,400, and two earlier change orders added $650. Under the old tub they find a rotted subfloor, and the customer decides to supply their own vanity.
| Line | Amount |
|---|---|
| Original contract | $18,400.00 |
| Earlier change orders | +$650.00 |
| Add: replace rotted subfloor, 40 sq ft | +$780.00 |
| Add: GFCI outlet by vanity | +$185.00 |
| Remove: vanity (customer supplied) | -$420.00 |
| This change order | +$545.00 |
| New contract total | $19,595.00 |
The schedule moves 2 days, from Dec 16 to Dec 18, 2026.
| Situation | Change order? |
|---|---|
| Customer adds or upgrades anything | Yes, before you start it |
| Hidden damage found (rot, old wiring) | Yes, with photos |
| Customer removes work or supplies materials | Yes, as a credit |
| A question about the plans (RFI) | Only if the answer changes the work |
| You fix your own mistake | No |
Keep each signed change order with the contract, numbered CO-1, CO-2 and so on, so your change order log is the stack of signed forms.
Prefer a paper change order form for construction? Download a free change order template. No email needed.
Name the project and the original contract, list the work added and removed with prices, show the original amount, earlier change orders and the new contract total, give the schedule change in days and the reason, then have both sides sign. The change order template above does the math and makes the PDF.
A change order form is a short written agreement that changes the scope, price or schedule of a signed contract. It protects you and the customer: nobody argues later about what extra work was asked for or what it costs.
An RFI (request for information) asks a question about the plans or specs, like which tile goes where; it does not change the price. A change order changes the scope, price or schedule and needs both signatures. An RFI answer often leads to a change order when it adds or removes work.
Price it the same way as the original job: your labor hours and materials at cost, plus your markup for overhead and profit. Removed work becomes a credit at the price it had in the contract. The markup calculator helps you set the price.
It is safer not to. Without a signed change order you may have trouble getting paid for the extra work, and some states require written change orders on home improvement contracts. This is general information, not legal advice.